Where to open a saved version
- On a customer opportunity row, next to Join, each saved version is an outline button. The label is the version name, or Estimate / Estimate vN when it has no name. Buttons do not show prices. When nothing is saved yet, the row still uses the products-step Estimate link.
- On the appointment block in the customer flyout, the same outline buttons appear under Estimates.
- The detailed Estimates section lower in the flyout is unchanged: each row still has Open, a status badge, version number and (for roles that can see them) a total.
- Open on an estimate row in the Sales Kanban flyout loads that exact version, with every door, labor, component, hardware and repair line and its openings.
/catalog/pricebook/estimate) for that customer, opportunity and version. The buttons match Join (same height, padding, corner radius and type size; white fill with outline) and look the same for every role that can see the row.
- If you open the estimate another way and the builder is empty, it loads the newest saved version that has lines.
- If you already have unsaved lines in this browser tab, they’re kept. Field Ops never replaces work you’re in the middle of.
- After the version loads, refreshing the page keeps your latest edits instead of reloading the saved version over them.
No new version when nothing changed
When you open a saved version and don’t change anything, Save version, copying the proposal link, publishing and sending all keep using that same version. No copy is added, so the opportunity row and the Estimates list don’t fill up with v3, v4 and v5 of the same estimate. The next version number is saved only when the estimate itself changes:- A door, labor, component, hardware, repair or manual line is added, removed or changes quantity.
- The total changes.
- The payment option changes on a version that was saved with one.
- Typing a new name in Save version without changing the estimate.
- A product photo or customer photo loading from a fresh link.
- An older version saved before Field Ops remembered the payment option. Opening it picks a payment option, and that alone doesn’t add a version.
Reopen an estimate from its proposal
You can reopen the estimate even when nobody pressed Save version. That happens when you sell straight through a proposal: publish it, send it or have the customer sign it, without saving a version first. When an opportunity (or a customer with no opportunity) has no saved version with lines, the estimate builder fills its cart from the latest proposal. A signed proposal is used first. Otherwise it’s the proposal that was updated most recently. Where to find it: the opportunity row on the customer page, the Estimates row in the customer flyout and the appointment flyout show Open estimate from proposal YND-xxxx, with that proposal’s number. It opens the estimate on step 4 (Estimate).- The lines, quantities (including half steps like 1.5) and prices come from the proposal.
- It’s a working copy. You can change quantities, add doors and change build options.
- Save version saves your edited cart as a new saved version. Publish and revise work the same as always.
- The proposal itself is never changed, even a signed one. Its lines, total and snapshot stay exactly as the customer saw them.
- A saved version with lines always wins. If one exists, you get the normal saved version buttons instead.
Workbench’s Accept on customer’s behalf hasn’t changed. It still shows only on a sent or viewed proposal, and a signed proposal hides it.
Custom doors that had no price-book code come back as manual lines, keeping their name, quantity and price. If the proposal’s lines were spread across more than one opening, check the openings rail and assign them again.
Next
Filter the price book
Narrow the products you see while you build an estimate.
Price book: all tasks
Every task for this area.